REPEAT ORDER FOR TAIWANESE STEELWORKS

 In September, SKAKO VIBRATION secured a repeat order to supply 12 screens and 21 feeders, for the second phase of the blast furnace extension at Dragon Steel Corporation, Taiwan.

Two years ago, SKAKO VIBRATION secured the order to supply an identical quantity of screens and feeders for the first phase of the steel works, through the main contractor Siemens VAI, and steel production commenced in February 2010. Following the success of the first phase, Siemens VAI were awarded the second phase, which will double the plants capacity.

The screens and feeders will be shipped in the first half of 2011, and they should be put into production in early 2012.